INSIDE IOWA STATE
June 29, 2001
 |
Ahead of schedule
Good news for Stange Road travelers: Project officials hope to have
construction completed and the south end of the road open to traffic by
mid-July. According to project manager Mike Parsons, sidewalks and retaining
walls are finished; work is under way on the fine grading and siding. In
addition, a guard railing will be installed on top of the barrier wall
constructed between the road and sidewalks. Photo by Bob Elbert.
|
|
Ames, Iowa 50011, (515) 294-4111
Published by: University Relations,
online@iastate.edu
Copyright © 1995-2001, Iowa State University. All rights reserved.
|
|