 |
|
|
INSIDE IOWA STATE
June 8, 2001
Coming to a lot near you: building construction
by Anne Krapfl
Take frequent hikes around campus in the coming months; most likely,
there's a new building going up near you. While state cuts to Iowa State's
operating budget for FY02 probably will result in program and position
reductions, the university's construction plans are moving forward.
Building funds typically come from capital project funds from the state and
from private fund raising, done over several years, and can't be used to
solve the university's operating budget shortfall.
Here's a quick rundown of some of the more visible projects that will add
to the changing ISU landscape in the months ahead:
- College of Business building. This three-story building will go up
on the southeast corner of central campus, on the site of Osborn Cottage.
University officials looked into the feasibility of moving the cottage and
donating it to Habitat for Humanity. However, estimates exceed $100,000, due
to the presence of asbestos and lead paint. So, pending approval this month
from the Board of Regents, State of Iowa, the plan is to demolish Osborn
Cottage. If approved, the demolition would take place in late August or
early September. A construction contractor for the Business building will be
selected in October, with work beginning yet this fall. The anticipated
completion date for the building is December 2003. Nearly $13.4 million of
the $24.5 million cost is private funds, with the Legislature appropriating
the remaining amount this session.
- (Phase 2 of the Engineering Teaching and Research
Complex). The three-story building will be located on Bissell Road, north of
Black Engineering. It will be built of the same materials as Howe Hall. A
contractor will be selected in August, with construction beginning this
fall. A July 2003 completion date is the goal. Nearly $30.3 million of the
building's $63.6 million price tag is from private funds.
- Honors Program building. The site for this two-story building is south
of Horticulture Hall, fringing the northeast corner of central campus.
Pre-construction site work is under way by Harold Pike Construction, Ames.
The scheduled completion date is February 2002. About $1.4 million of this
project's $2.2 million cost is in private funds. The Honors Program,
previously housed in Osborn Cottage, will move to Pearson Hall for the
2001-02 school year.
- Extension 4-H Youth building. This building will be located at the
southwest corner of the Stange Road-13th Street intersection, north of the
Administrative Services Building. $2.5 million of its proposed $4.5 million
price tag comes from private gifts; extension leaders await regents'
approval on the last $1 million.
- Bus terminal in the Iowa State Center parking lot. The site is along
the existing CyRide route in the southwest quadrant of the lot. The $325,000
facility includes an indoor heated area with restrooms, and protected but
unheated outdoor shelter area with bench seating. Funding sources for this
facility are the ISU parking division and Government of the Student Body.
The facility should be done by January.
- Carver Co-laboratory. This research facility will be located north of
the Molecular Biology Building. Slated to begin this summer, construction
has been delayed because a basement level, housing more laboratory and
support space, is being added to the project. A groundbreaking ceremony will
be held Oct. 20. At their May meeting, the regents approved a new budget,
$12.75 million (up from $9.5 million).
Residence department Master Plan projects
- Union Drive suite building (first of three). The location for
these four-story residence halls is south of State Gym, on the former Clyde
Williams field. Site work for the first building began in late April. Henkel
Construction Co., Mason City, is the contractor. The scheduled completion
date is August 2002. This $23.7 million project includes adding utilities
for the whole project.
- Union Drive community center. A three-story $15 million building will
be located east of State Gym, on the site of the Helser Hall north wing,
which is being demolished. Design of the building is in progress. The
project schedule calls for the contractor to be selected in February or
March 2002, with work beginning shortly after. The anticipated completion
date is July 2003.
- Hawthorn Court. This north-campus residence neighborhood consists of
23 apartment buildings and a community center. The first nine apartment
buildings opened in July 2000 and three more were completed during fall
semester 2000. Another seven apartment buildings and the community center
will open in August. The last four apartment buildings will be completed
throughout the fall semester.
|
Ames, Iowa 50011, (515) 294-4111
Published by: University Relations,
online@iastate.edu
Copyright © 1995-2001, Iowa State University. All rights reserved.
|
|